Laytime: Calculation, Terms and Charter Party Clauses
Laytime is the time a voyage charter allows for loading or discharge before demurrage runs: how it starts, stops, is counted and calculated under GENCON 2022.
Contents21 sections
Laytime is the period a voyage charter allows the charterer for loading or discharging the cargo without paying anything beyond the freight. Definition 5 of the Laytime Definitions for Charter Parties 2013 puts it as the period agreed between the parties “during which the owner will make and keep the Vessel available for loading or discharging without payment additional to the freight.” Time used beyond it is paid as demurrage; time saved may earn despatch.
The clock starts at a point the charter fixes after a valid notice of readiness at an arrived ship, usually a notice period or a start hour later. It stops for what the day terms exclude, such as holidays under SHEX and SHINC or weather under the weather working day, and for named exceptions like shifting, strikes and gear breakdown. It ends at completion of cargo operations as the charter defines it. The answers come from the charter party wording, read with the 2013 Definitions where they are incorporated, and from English case law, where most of the reported authority on the standard forms has been decided.
What laytime is and where it is defined
Laytime is a term of the voyage charter party and of the contract of affreightment. The freight pays the owner for the voyage including an agreed allowance of port time; laytime is that allowance. Under a time charter party the charterer pays hire for all time, and lost time is dealt with by the off-hire clause, so there is no laytime account at all.
The Laytime Definitions for Charter Parties 2013 are the standard set of meanings. FONASBA publishes them as VOYLAYRULES 2013 and lists them as jointly issued by BIMCO, the Comité Maritime International, FONASBA and INTERCARGO. BIMCO Special Circular No. 8 of 10 September 2013 records that BIMCO’s Documentary Committee adopted them in Paris in May 2013, after drafting by a group drawn from the original sponsors together with a participant from the Baltic Exchange. The document carries 33 numbered definitions. It has no articles, and it defines no SHEX, SHINC, “even if used”, “arrived ship” or turn time.
Predecessors and incorporation
The 2013 text is the successor to two earlier codes. CMI began the project in 1976, and a working group of BIMCO, CMI, the UK Chamber of Shipping and FONASBA produced the Charter Party Laytime Definitions 1980. After a critical 1990 UNCTAD report they were revised and issued as the Voyage Charter Party Laytime Interpretation Rules 1993, Voylayrules 1993. The 2013 circular does not withdraw either, so a charter that incorporates Voylayrules 1993 is still read under Voylayrules 1993.
The definitions bind only when the charter incorporates them. BIMCO’s recommended wording incorporates them “in full” and gives them priority over any conflicting provision. GENCON 2022 Clause 10(a) does the reverse: it deems them incorporated “except where inconsistent with its terms”, so the printed GENCON wording wins. A GENCON 1994 fixture gets them only if the rider says so, and a fixture on any form can still depart from a definition by express words.
The 2013 revision changed five things a practitioner meets in a dispute, according to the circular:
- It restored three separate meanings of weather working day (definitions 15 to 17) “in line with English law decisions”, where Voylayrules 1993 had merged them into one.
- It deleted the Voylayrules definition of “Strike” and the “In Writing” rule.
- It added Calendar Day, Conventional Day, Running Hours, Always Accessible and WIPON.
- It changed WIBON (definition 27) so that time runs as the charter provides, rather than stopping when the berth becomes free.
- It qualified the demurrage definition (definition 30) so that laytime exceptions do not apply to demurrage “unless specifically stated in the Charter Party”.
How laytime is fixed
Laytime is fixed in one of two ways: as a number of days or hours, or as a rate of loading or discharging applied to the cargo quantity. GENCON 2022 Box 17 asks the parties to “state days or rate, and if SHINC or SHEX” for each of loading and discharging, or for a single total. Clause 10(b) then requires the cargo to be loaded “either within the number of running days or at the rate stated in Box 17(i), except to the extent that the actual loading is delayed or prevented by weather”, with the same wording for discharge.
Tanker forms fix laytime in hours. ASBATANKVOY 1977 Clause 7 permits the charterer “the number of running hours specified as laytime in Part I” for loading and discharging together. Running hours, under definition 13, are hours “which follow one immediately after the other”. The 2013 revision added the definition with tanker charters in mind.
Rate-based laytime and the hatch formulas
A rate per day converts into laytime by division. Cargo of 32,500 tonnes at 10,000 tonnes per day gives 3.25 days, or 78 hours. Bulk charters sometimes tie the rate to the ship’s hatches instead, and definitions 6 and 7 give the two formulas BIMCO says are still used “to a limited extent”.
Definition 6, per hatch per day:
$$ \text{Laytime (days)} = \frac{\text{Quantity of cargo}}{\text{Daily rate} \times \text{Number of hatches}} $$Definition 7, per working hatch per day or per workable hatch per day:
$$ \text{Laytime (days)} = \frac{\text{Largest quantity in one hold}}{\text{Daily rate per hatch} \times \text{Number of hatches serving that hold}} $$Under both definitions each pair of parallel twin hatches counts as one hatch, and a hatch that two gangs can work at the same time counts as two. Definition 7 reflects how a bulk carrier is actually worked: the hold with the most cargo finishes last, so it sets the time. On a ship with uneven stowage the two formulas give different answers for the same cargo.
Day definitions in the Laytime Definitions 2013
A laytime clause counts in days, and the 2013 Definitions give the day five distinct meanings. The choice decides how many clock hours a “day” of laytime consumes.
| Definition | Term | Meaning (2013 text) |
|---|---|---|
| 8 | Day | 24 consecutive hours; any part of a Day counted pro rata |
| 9 | Calendar Day | 24 consecutive hours running from 0000 to 2400 hours |
| 10 | Conventional Day | 24 consecutive hours running from any identified time |
| 11 | Working Day | A Day when by local law or practice work is normally carried out |
| 12 | Running Days or Consecutive Days | Days which follow one immediately after the other |
| 13 | Running Hours or Consecutive Hours | Hours which follow one immediately after the other |
| 14 | Holiday | A Day other than the normal weekly rest days, or part of one, when by local law or practice work in ordinary working hours is not normally carried out |
Working day and holiday are both tied to local law or practice, so the same charter produces different laytime at different ports. A Saturday is a working day at one port and a customary day of rest at another. The port agent is usually the first source of the local position, and a disputed point goes to evidence of local practice.
Weather working days and the 48-hour wording
The 2013 Definitions give the weather working day three meanings, plus a fourth phrase that shares one of them. Each deducts weather differently.
| Definition | Term | How weather is deducted |
|---|---|---|
| 15 | Weather Working Day | A period proportional to the working time lost, measured against the time that would or could have been worked |
| 16 | Weather Working Day of 24 Consecutive Hours | The actual period during which weather interrupted or would have interrupted work, at any time of the working day |
| 17 | Weather Working Day of 24 Hours | The actual period of interruption, within an artificial day of 24 hours “made up of one or more Working Days” |
| 18 | (Working Day) Weather Permitting | Same meaning as definition 16 |
All three apply while the ship is still waiting for her turn: each covers time when “it would be possible to load/discharge the cargo without interruption due to the weather”, so rain at the berth deducts time even before the ship is alongside.
BIMCO Special Circular No. 8 works the arithmetic. Under definition 15, a two-hour stoppage in an eight-hour working day deducts six hours of laytime, because a quarter of the working day was lost; on a twelve-hour working day the same stoppage deducts four hours. Rain outside normal working hours deducts nothing. Under definition 16 the deduction is the actual length of the interruption at any time on a working day, including outside normal hours and while the ship is waiting for her turn.
The cumulative day and the 48-hour queries
Definition 17 is the cumulative day. It builds one laytime day out of 24 hours of working time, so the circular’s example gives a port working eight hours a day three calendar days for each laytime day. That is the meaning behind charter wording about weather working days counted in cumulative hours.
The Laytime Definitions 2013 contain no 48-hour unit. A clause reading “48 hours good weather working days” or “cumulative 48 hours” is not a defined term. It is construed on its own words, and where it describes laytime built up from working hours, definition 17 is the nearest defined meaning. A fixture that means something else, such as two consecutive 24-hour periods under definition 16, has to say so.
The printed GENCON 2022 laytime clause does not use the weather working day. Its Clause 10(b) counts running days or a rate “except to the extent that the actual loading is delayed or prevented by weather”. The charter-specific good weather definitions used in speed and consumption warranties are a separate subject.
SHEX, SHINC, excepted periods and unless used
SHEX and SHINC are not defined in the Laytime Definitions 2013; GENCON 2022 defines them in Clause 10(a). SHINC means laytime is “to run continuously and without interruption for public holidays or customary days of rest at the port or place in question, whether or not work is done at overtime rates”. SHEX means “there shall be excluded from laytime public holidays and customary days of rest at the port or place in question unless used.”
Two of the 2013 definitions decide what happens when cargo is worked on an excepted day:
- Definition 19, Excepted or Excluded: the days specified “do not count as Laytime even if loading or discharging is carried out on them”.
- Definition 22, Unless Used: if laytime has commenced and cargo is worked during excepted periods, “actual time used shall count as Laytime”.
The two point in opposite directions, so the charter wording matters. GENCON 2022 SHEX carries “unless used” in its printed definition: holiday hours actually worked count. A clause that says only that Sundays and holidays are excepted falls under definition 19, and hours worked on them do not count. “Even if used” (EIU) is market shorthand for the definition 19 result, written out to remove doubt. FHEX and FHINC, the Friday-and-holidays variants used where Friday is the weekly rest day, are likewise market abbreviations with no 2013 definition; their meaning comes from the clause.
BIMCO’s GRAINCON form shows how a grain clause combines these elements. Its laytime clause counts “working days of twenty-four (24) consecutive hours each, weather permitting, Sundays (or the local equivalent) and holidays excepted, unless used.” It adds a Saturday rule: a Saturday on which labor or facilities are unavailable, or available only at overtime, does not count, and six or more hours worked at normal rates counts as a full layday. While the ship waits for a berth, no weather deduction is made unless the ship occupying the berth is actually prevented from working by weather.
When laytime starts
Laytime starts at the point the charter fixes, which is rarely the moment the notice of readiness is tendered. Three conditions come first: the ship must be an arrived ship, she must be ready to load or discharge, and the notice must be validly tendered. The notice of readiness article covers each in detail. Then the charter adds a notice period or a fixed start hour.
GENCON 2022 Clause 11 starts laytime at the earlier of the commencement of cargo operations and a fixed hour. On SHEX terms that hour is 14.00 local time if notice is tendered up to and including noon on a working day, 08.00 on the next working day if tendered after noon, and 14.00 on the next working day if tendered on a non-working day. On SHINC terms the morning rule is the same, and an afternoon tender during office hours starts laytime at 08.00 the next day. There is no turn time in the printed GENCON 2022 text.
The tanker forms use six hours of notice time:
- ASBATANKVOY 1977 Clause 6: notice is given “upon arrival at customary anchorage”, and laytime commences “upon the expiration of six (6) hours after receipt of such notice”, berth or no berth, or on arrival in berth if earlier.
- SHELLVOY 6 Clause 13(1)(a): time runs six hours after notice is tendered or when the ship is securely moored at the berth, whichever is first. The notice is invalid if free pratique is not obtained within the six hours, unless it is not customary before berthing.
- BPVOY4 Clause 7.3.2: laytime or demurrage commences six hours after a valid notice “has become effective”, berth or no berth, or when loading or discharging starts, whichever is first. Under Clause 6.3.2 the notice takes effect only once the ship has anchored where ships of her type customarily anchor, or has reached the customary waiting area.
Cargo work during turn time
Turn time is the interval between notice and the start of laytime, and the 2013 Definitions use the word without defining it. Two definitions deal with cargo work done inside it. Under definition 20, “unless sooner commenced”, laytime commences when loading or discharging begins during turn time. Under definition 21, “unless sooner commenced, in which case actual time used to count”, only the hours actually worked during turn time count, and laytime proper starts when turn time expires.
Waiting for a berth
Who pays for time at anchor depends on the berth or port clause. Under a berth charter without a waiting clause the ship is not arrived until she reaches the berth, so the owner bears the wait. GENCON 1994 Clause 6 shifted it with the words “time lost in waiting for berth to count as loading or discharging time”, which definition 26 of the 2013 Definitions also covers under time lost waiting for berth. WIBON and WIPON clauses let notice be tendered whether in berth or not, or in port or not; BIMCO’s commentary on definition 27 says WIBON “relates to delays due to congestion (but not on account of weather)”.
Two House of Lords cases on ASBATANKVOY Clause 6, as summarized by Moore-Bick J in The Nikmary [2003] EWHC 46 (Comm), set the tanker position. In The Laura Prima [1982] 1 Lloyd’s Rep 1, charterers had agreed a berth “reachable on arrival”, so the proviso excusing “delay … getting into berth” did not cover congestion, and the waiting time counted against them. In The Notos [1987] 1 Lloyd’s Rep 503 there was no reachable on arrival undertaking, and delay caused by swell making a sea-line unusable did not count.
Exceptions and interruptions
An exception stops laytime only for the event and the period the clause names, and the charterer has to prove it. In The Ladytramp [2013] EWCA Civ 1449 the Court of Appeal treated the burden as on charterers to show that delay at Paranagua was caused by a “mechanical breakdown” at the loading plant under the clause in their Sugar Charter Party 1999 fixture. It held that destruction of the plant’s machinery by fire did not “without more” amount to a mechanical breakdown.
The standard exceptions, by subject:
- Weather. Under the weather working day definitions, or the GENCON 2022 Clause 10(b) proviso for loading or discharge “delayed or prevented by weather”.
- Shifting. GENCON 2022 Clause 12(a) makes shifting to a second berth at the same port, or out of and back to the same berth, count as laytime or time on demurrage unless it is for the owners’ purposes; charterers pay for tugs and pilots. BPVOY4 Clause 5.3 counts shifting time “except as otherwise provided in Clauses 17 and 18.2”. SHELLVOY 6 Clause 9 counts time shifting off a berth made dangerous “as a result of wind or water conditions”.
- Ship’s gear. GENCON 2022 Clause 4(c): time actually lost by breakdown of the vessel’s cargo-handling gear or lack of sufficient power does not count as laytime or time on demurrage, unless the charterers’ side caused or contributed to it. ASBATANKVOY 1977 Clause 7 excludes “any delay due to the Vessel’s condition or breakdown or inability of the Vessel’s facilities to load or discharge cargo within the time allowed”.
- Owners’ fault. SHELLVOY 6 Clause 14(c)(i) stops time lost “as a result of … breach of this Charter by Owners”, and Clause 7 stops time lost to the owners’ failure to provide mooring or hose personnel and equipment.
- Strikes. GENCON 2022 Clause 17, under the strike rules below.
- Cargo and environment. GENCON 2022 Clause 12(b) counts delay from “environmental or public health concerns relating to the Cargo”, with dust suppression at charterers’ expense.
Cargo not being ready is not an exception. In The Nikmary the charterer had “an absolute obligation to provide a cargo”, though it only needed to have the cargo ready in time to complete loading within the laytime. Delay caused by its failure to have cargo available fell outside the ASBATANKVOY Clause 6 proviso for delay “over which Charterers have no control”.
Strike clauses
GENCON 2022 Clause 17 gives strikes their own scheme rather than a simple exception. If a strike affects loading before it begins, owners may ask charterers to confirm that laytime and demurrage will count as if there were no strike, and may cancel if no written confirmation arrives within 24 hours. Once loading has begun, strike delay runs as demurrage “at half rate for the first ten (10) cumulative days and thereafter … at full rate”. After a cumulative total delay of 25 days, owners are paid the higher of the demurrage rate and “the prevailing market hire rate plus bunkers consumed”. The clause applies the same scheme at discharge. Other forms handle strikes differently; strike clauses in voyage charters compares them.
When laytime ends
Laytime ends at completion of cargo operations as the charter defines completion. GENCON 2022 Clause 12(c) runs laytime or demurrage “continuously until completion of Cargo operations, which includes the removal of any stevedores’ equipment from the Vessel”. Charterers then get “three hours after completion of cargo operations at each loading port” to provide the cargo documents, after which time runs again until they are received. BPVOY4 Clause 7.3.3 stops time “until the cargo hoses have been finally disconnected upon completion of loading or discharging”.
GENCON 2022 Clause 10(c) deals with short-shipment. Where laytime is calculated on the quantity shipped and the charterers pay full freight on a short-shipment, laytime is calculated on the bill of lading quantity plus the short-shipped quantity. The owner’s laytime is not reduced by cargo the charterer failed to supply. Freight on the unshipped cargo is a deadfreight question.
Laytime calculation: worked example
Laytime used is the time between commencement and completion, less excepted periods, plus any time worked in an excepted period that an “unless used” proviso brings back in.
Laytime Used
where
| \(T_{\text{start}}\) | Laytime commencement under the charter: expiry of any notice time after a valid NOR, a fixed start hour, or earlier start of cargo work where the charter or LDCP 2013 def. 20 so provides | h |
| \(T_{\text{end}}\) | Completion as the charter defines it, e.g. hoses disconnected or stevedores' equipment removed | h |
| \(\text{Excepted}\) | Periods the charter excludes: holidays and rest days under SHEX, weather, strikes, owners' gear breakdown and other excepted events, counted only before laytime expires (LDCP 2013 def. 30) | h |
| \(\text{Used}_{\text{exc}}\) | Time actually worked in excepted periods where an unless-used proviso applies (LDCP 2013 def. 22) | h |
Source: BIMCO Laytime Definitions for Charter Parties 2013, defs 5 and 19 to 22; BIMCO GENCON 2022, Clauses 10 to 12
The example applies GENCON 2022 unamended, SHEX terms, 32,500 tonnes at 10,000 tonnes per day, and an assumed demurrage rate of USD 18,000 per day pro rata. It is constructed to show the method; the rate and times are illustrative, not market data. Laytime allowed is 32,500 / 10,000 = 3.25 days, or 78 hours.
The ship anchors at the customary anchorage on Monday and the master tenders a valid notice of readiness at 10.30, before noon on a working day. Under Clause 11(b)(ii) laytime starts at 14.00 on Monday; the ship berths at 12.00 and loading begins at 14.00. Rain stops loading at the berth from 03.00 to 07.00 on Tuesday. Wednesday is a public holiday on which the charterers work cargo from 08.00 to 16.00. Loading completes, stevedores’ equipment off, at 10.00 on Saturday, which is a working day at this port, and the cargo documents are on board within the three hours Clause 12(c) allows.
| Period | Clock hours | Excepted | Counts |
|---|---|---|---|
| Monday 14.00 to 24.00 | 10 | 0 | 10 |
| Tuesday 00.00 to 24.00 | 24 | 4 (rain, Clause 10(b)) | 20 |
| Wednesday 00.00 to 24.00, public holiday | 24 | 24 (SHEX), less 8 hours worked that count back under “unless used” | 8 |
| Thursday 00.00 to 24.00 | 24 | 0 | 24 |
| Friday 00.00 to 16.00 | 16 | 0 | 16 |
| Laytime expires Friday 16.00 | 78 | ||
| Friday 16.00 to Saturday 10.00, on demurrage | 18 | not applied (definition 30) | 18 hours demurrage |
Demurrage is 18 hours, or 0.75 days, so 0.75 × USD 18,000 = USD 13,500. If rain had fallen on Friday evening, it would still count, because the ship was on demurrage and definition 30 keeps laytime exceptions out of demurrage unless the charter says otherwise.
Change two words to see what “unless used” is worth. If the clause excepted holidays without “unless used”, definition 19 applies and Wednesday’s 8 working hours do not count. Laytime then expires 8 hours later, at 00.00 on Saturday, and demurrage falls to 10 hours: 10 / 24 × USD 18,000 = USD 7,500. The two words cost the charterer USD 6,000 on this fixture.
The demurrage step is the second card. ShipCalculators.com runs the same calculation from laytime allowed, laytime used and the rate.
Days & USD
where
| \(allowed\) | Laytime allowed by the charter party | days |
| \(used\) | Time counting against the charterer: laytime used up to expiry, plus all time from expiry to completion except periods the charter specifically excludes from demurrage (laytime exceptions do not apply after expiry) | days |
| \(r\) | Demurrage rate stated in the charter, pro rata for part periods; a rate per running hour is multiplied by 24 to give the daily figure | USD/day |
Source: BIMCO Laytime Definitions for Charter Parties 2013, defs 8 and 30 (Day pro rata; demurrage after laytime expires, not subject to laytime exceptions unless the charter specifically says so); GENCON 2022 Box 19 and Clause 13; ASBATANKVOY (1977) Part II Clause 8; BPVOY4 Clause 7.4. Half-rate periods under these clauses are priced at r/2 and are not modelled by this card
Once on demurrage, always on demurrage
Once laytime has expired, laytime exceptions stop applying unless the charter extends them to demurrage. Definition 30 of the 2013 Definitions puts the rule into the definition itself: demurrage is “an agreed amount payable to the owner in respect of delay to the Vessel once the Laytime has expired, for which the owner is not responsible. Demurrage shall not be subject to exceptions which apply to Laytime unless specifically stated in the Charter Party.”
The House of Lords explained the reason in Dias Compania Naviera SA v Louis Dreyfus Corporation (The Dias) [1978] 1 WLR 261. Lord Diplock, as quoted in The Eternal Bliss [2020] EWHC 2373 (Comm), said that if laytime ends before the charterer has finished discharging “he breaks his contract”, that the breach is a continuing one, and that demurrage is the liquidated sum that “accrues throughout the period of time for which the breach continues”. An exception written for laytime describes when time is not used up; it does not excuse a breach already running.
The rule yields to clear words. GENCON 2022 Clause 13(b) lets demurrage accrue “continuously and without interruption”, except for time actually lost because the vessel is not available to perform the service required, unless the charterers caused that. In The John Michalos [1987] 2 Lloyd’s Rep 188, as summarized in The Eternal Bliss [2020] EWHC 2373 (Comm), Leggatt J held a voyage charter exceptions clause clear enough to relieve the charterer of demurrage for a strike that began after the ship was already on demurrage. The once on demurrage stub collects the authorities.
Half-rate demurrage clauses
Several forms let demurrage run during particular delays but at a reduced rate. SHELLVOY 6 Clause 15(2), as quoted in The Stena Primorsk [2022] EWHC 2147 (Comm), counts delays not allocated elsewhere in the charter and beyond the reasonable control of either party as laytime or demurrage, with demurrage “paid at half the Demurrage Rate”. BPVOY4 Clause 7.4 reduces the rate “to one-half” for demurrage incurred through the causes in its Clause 17. GENCON 2022 Clause 17 applies half rate to the first ten days of strike delay. Half-rate demurrage compares them.
Demurrage as the exclusive remedy for delay
Demurrage is the whole of the owner’s remedy for the charterer’s failure to complete cargo work within laytime. In The Eternal Bliss [2021] EWCA Civ 1712, a 70,133-tonne soybean cargo at a USD 20,000 per day demurrage rate, the owner settled a cargo deterioration claim and sought to recover it from the charterer as damages for delay.
The Court of Appeal held that “the charterer is not liable to pay damages in addition to demurrage” for failing to complete discharge within the laytime. Extra damages need a breach of “a separate and distinct obligation”. The court endorsed The Bonde [1991] 1 Lloyd’s Rep 136, decided by Potter J at first instance, which it said “has now stood for some 30 years”. The demurrage article’s exclusive remedy section takes the point further.
Reversible, averaged and non-reversible laytime
Separate laytime is calculated port by port unless the charter allows the two ends to be combined. The 2013 Definitions give two ways to combine them:
- Definition 24, reversible laytime: “an option given to the charterer to add together the time allowed for loading and discharging. Where the option is exercised the effect is the same as a total time being specified to cover both operations.”
- Definition 23, to average laytime: “separate calculations are to be made for loading and discharging and that any time saved in one operation is to be set off against any excess time used in the other.”
Read with definition 30, the difference shows when the ship goes on demurrage at the first port. Under reversible laytime the ship is on demurrage from the moment the combined allowance runs out, so exceptions stop applying from that point on. Under averaging, each port keeps its own laytime count with its own exceptions, and the net is struck at the end. BIMCO’s commentary on definition 24 adds that reversibility works between loading and discharging ports, not between two loading ports or two discharging ports.
GENCON 2022 Clause 10(b)(i) states that separate laytime for loading and discharging “shall be non-reversible”. Charterers who want reversibility fix a total under Box 17(iii) or write it into the rider. Reversible laytime and despatch covers the arithmetic, and laytime averaging the definition 23 method.
Despatch money and the time-saved basis
Despatch is the owner’s payment to the charterer for finishing early. Definition 31 calls it “an agreed amount payable by the owner if the Vessel completes loading or discharging before the Laytime has expired.” It is payable only where the charter provides for it.
The basis of the saving matters as much as the rate:
| Definition | Basis | Counts excepted periods after completion? |
|---|---|---|
| 32 | Despatch on all working time saved, or on all laytime saved | No |
| 33 | Despatch on all time saved | Yes |
GENCON 2022 Clause 13(a) pays despatch “at half the demurrage rate on all laytime saved”. Clause 10(a) incorporates the 2013 Definitions, and definition 32 treats “all laytime saved” and “all working time saved” as one term, so a GENCON 2022 fixture does not pay despatch for a weekend or holiday that falls between completion and the expiry of laytime. A fixture on “all time saved” would pay for it.
Statement of facts and time sheet
The laytime account is built on two documents. The statement of facts records the events: arrival, notice tendered and accepted, free pratique, berthing, start and stop of cargo work, every stoppage with its cause, completion and departure. The time sheet applies the charter terms to those events and arrives at laytime used, demurrage or despatch.
BIMCO’s current forms are the Standard Statement of Facts (short form) and the Standard Time Sheet (short form), both published in 1975 and recommended by BIMCO and FONASBA. BIMCO describes the time sheet as a document “to assist in the calculation of laytime”. The port agent usually prepares the statement of facts, and a letter of protest is the usual way to put a disputed entry on record.
The entries carry the burden of proof. Because the charterer has to bring a delay within an exception, as The Ladytramp [2013] EWCA Civ 1449 confirms, a stoppage recorded only as “no work”, with no cause, gives the charterer nothing to prove the exception with.
Laytime clauses in the standard forms
Each standard form sets laytime with its own clauses, and the clause numbers below belong to the edition named. A recap on a later edition or with a rider has to be read on its own text.
| Form | Laytime fixed | Commencement | Notable laytime terms |
|---|---|---|---|
| GENCON 2022 (BIMCO) | Box 17, Clause 10(b): running days or rate, weather excepted, separate laytime non-reversible | Clause 11: 14.00 or 08.00 local time, or earlier cargo operations | Clause 10(a) SHEX “unless used”; 12(a) shifting counts; 4(c) gear breakdown excepted; 13(b) continuous demurrage; 17 strikes |
| GENCON 1994 (BIMCO) | Clause 6 | Clause 6 | “Time lost in waiting for berth” counts; 2013 Definitions only if incorporated |
| ASBATANKVOY 1977 | Clause 7: running hours stated in Part I | Clause 6: six hours after notice at customary anchorage, or on berthing | Delay getting into berth for reasons beyond charterers’ control does not count; Clause 7 excludes ship’s condition |
| SHELLVOY 6 | Part I | Clause 13(1)(a): six hours after notice or when moored, whichever first | Clause 9 weather shifting counts; 14 owners’ breach; 15(2) half rate for unallocated delays |
| BPVOY4 | Part I | Clause 7.3.2: six hours after notice effective, or on start of cargo work | 5.3 shifting counts; 7.3.3 ends at hose disconnection; 7.4 half rate for Clause 17 causes; 20.1 90-day claim bar |
| GRAINCON (BIMCO) | Laytime clause: working days of 24 consecutive hours, weather permitting, Sundays and holidays excepted unless used | 08.00 on the next day not excepted after notice | Saturday rule; no weather deduction while waiting unless the berth’s occupant is stopped |
ASBATANKVOY was revised in 2025: BIMCO and the Association of Ship Brokers and Agents published ASBATANKVOY 2025 on 23 April 2025. The clause numbers in the table are those of the 1977 printed text as quoted in The Nikmary, a charter with Vitol amendments, so a 2025 fixture needs its own clause check. SHELLVOY 6 and BPVOY4 are oil-major forms: the SHELLVOY 6 wording above is as amended in The Stena Primorsk fixture, and the BPVOY4 wording is the printed Part 2 quoted in The Abqaiq [2011] EWCA Civ 1127. GRAINCON and SYNACOMEX 2023 are grain forms, alongside the older NORGRAIN 89; the coal form AMWELSH 93 and the tanker forms Tankervoy 87 and BIMCHEMVOY 2008 each carry their own laytime clauses. Every GENCON edition’s commencement rules differ, and the notice of readiness article sets them side by side.
Laytime claims, time bars and disputes
A laytime claim is a demurrage or despatch claim, and the charter’s claims clause decides how long the owner has to make it. BPVOY4 Clause 20.1 releases charterers from demurrage claims unless a written claim “together with all supporting documentation substantiating each and every constituent part of the claim” is presented within 90 days of completion of discharge. In The Eagle Valencia [2010] EWCA Civ 713, the charter’s SHELLVOY 5 Part II Clause 15(3), as amended, required notice within 60 days and documents within 90 days.
On the clause’s words, a claim presented within the period but without the documents it names does not stop the release, which is why the documents matter as much as the date. Demurrage time bars and documentation sets out what each form requires.
Disputes on English-law forms go to London arbitration under the Arbitration Act 1996. A question of law reaches the court either as a preliminary point under section 45, by agreement of the parties or with the tribunal’s permission, as in The Eternal Bliss, or by appeal with permission under section 69.
A dispute about which party bears a delay through a charter chain is decided separately in each contract, so the head owner’s demurrage and the sub-charterer’s can differ for the same port call.
Laytime outside English law
Laytime is a creature of contract, so the terms the parties write govern wherever the dispute is heard. The Laytime Definitions 2013 apply in the same words wherever a charter incorporates them.
The Maritime Code of the People’s Republic of China 1992 lists laydays, loading and discharging time, demurrage and despatch among the contents of a voyage charter in Article 93, and leaves the time for loading and discharge, its calculation and the demurrage and despatch rates to the parties’ agreement in Article 98. The 1992 Code has no rule on notice of readiness or the start of laytime. A revised Maritime Code was adopted by the Standing Committee of the National People’s Congress on 28 October 2025 and took effect on 1 May 2026, and the 1992 article numbers may not carry over to the revised Code.
For a fixture governed by another law, the questions are the same: whether the laytime definitions were incorporated, how the clause allocates waiting time, and whether exceptions survive into demurrage. Local working days and holidays are always a question of the law or practice of the port, under definitions 11 and 14, whatever law governs the charter.
Laytime in the voyage estimate
Laytime is an input to every voyage estimate. The owner prices the freight on the port days the laytime allows, and demurrage earned beyond them is revenue only if collected. The estimate’s result feeds the time charter equivalent, so a fixture with generous laytime and a low demurrage rate can show a weaker TCE than the freight alone suggests.
Laytime terms also interact with a ship’s commercial position at the loading port. Port congestion moves money between owner and charterer through the waiting clauses, and just-in-time arrival clauses change when notice can be tendered. Free pratique, hold cleanliness and the stevedoring arrangements under FIO and FIOS terms each decide whether the ship was ready and who caused a stoppage.
Limitations
This article states the printed text of the forms and the Laytime Definitions 2013 as read, and English case law as reported. Every fixture is governed by its own recap and rider, which routinely amend the printed clauses. Clause numbers belong to the editions named; ASBATANKVOY 2025, SHELLVOY 6 and BPVOY4 wording above is taken from the text quoted in the judgments cited, which may include the parties’ amendments.
The worked example uses an assumed demurrage rate and invented times to show the method, and it applies GENCON 2022 without a rider. Demurrage rates vary with ship size, trade and market, and no market rate is stated here. The section on Chinese law reflects the 1992 Maritime Code; the revised Code in force from 1 May 2026 has not been checked article by article. US, civil-law and other jurisdictions’ treatment of laytime is not covered. This is reference material, not legal advice on any fixture.
Frequently Asked Questions (FAQs)
What is laytime?
Laytime is the period a voyage charter allows for loading or discharging the cargo.
Definition 5 of the Laytime Definitions for Charter Parties 2013 defines it as the period agreed between the parties during which the owner will make and keep the vessel available for loading or discharging without payment additional to the freight. Time used beyond it is paid as demurrage.
What is the difference between laytime and demurrage?
Laytime is time the charterer has already paid for in the freight.
Demurrage is the agreed amount per day, and pro rata for part of a day, payable to the owner once laytime has expired. Definition 30 of the Laytime Definitions 2013 adds that demurrage is not subject to the exceptions that apply to laytime unless the charter party specifically says so.
What is the difference between laytime and laydays or laycan?
Laytime is the time allowed for cargo work.
Laydays, in the laydays and cancelling (laycan) sense used in GENCON 2022 Box 18, is the window in which the ship must present herself at the first loading port, with the cancelling date as its end. A ship can arrive inside the laycan and still face a separate question of when laytime starts. Some older texts use laydays as a synonym for laytime, which is why the Scrutton definition quoted in The Eternal Bliss refers to ’the laydays or laytime'.
Who publishes the Laytime Definitions 2013, and do they apply automatically?
They were jointly issued by BIMCO, CMI, FONASBA and INTERCARGO, adopted at BIMCO’s Documentary Committee in Paris in May 2013 and circulated in BIMCO Special Circular No. 8 of 10 September 2013.
They apply only when a charter incorporates them. GENCON 2022 Clause 10(a) incorporates them except where inconsistent with its own terms; a GENCON 1994 fixture gets them only if the rider says so.
What did the Laytime Definitions 2013 replace?
They are the successor to the Charter Party Laytime Definitions 1980 and the Voyage Charter Party Laytime Interpretation Rules 1993 (Voylayrules 1993).
BIMCO Special Circular No. 8 does not withdraw either earlier text, so a charter that incorporates Voylayrules 1993 is still governed by Voylayrules 1993.
How is laytime calculated per hatch per day?
Under definition 6 of the Laytime Definitions 2013, laytime in days equals the quantity of cargo divided by the product of the daily rate and the number of hatches.
Each pair of parallel twin hatches counts as one hatch, and a hatch that can be worked by two gangs simultaneously counts as two.
How is laytime calculated per working or workable hatch per day?
Definition 7 divides the largest quantity in any one hold by the product of the daily rate per hatch and the number of hatches serving that hold.
The answer is the laytime in days. The largest hold governs because it is the last to finish when every hold is worked at the same rate.
What does '48 hours good weather working days' mean in a charter?
It is not a term defined in the Laytime Definitions 2013, which contain no 48-hour unit.
The defined weather terms are the weather working day (definition 15), the weather working day of 24 consecutive hours (definition 16) and the weather working day of 24 hours (definition 17). A clause using a 48-hour wording is construed on its own words; where it aims at a day built up from working hours, definition 17 is the closest defined meaning.
What does a cumulative weather working day of 24 hours mean?
Under definition 17, a weather working day of 24 hours is a period of 24 hours made up of one or more working days.
It is an artificial day of 24 working hours. BIMCO Special Circular No. 8 illustrates it: where the port works an 8-hour day, one such laytime day spans three calendar days. Weather interruptions are deducted at their actual length.
How is rain deducted from a weather working day?
Definition 15 deducts a period proportional to the working time lost.
BIMCO Special Circular No. 8 gives the example of a two-hour stoppage in an eight-hour working day, which deducts six hours of laytime, or four hours on a twelve-hour working day. Rain outside normal working hours deducts nothing under definition 15.
What is the difference between a weather working day and a running day?
Running days, under definition 12, are days that follow one immediately after the other, with no allowance for weekends, holidays or weather unless the charter adds one.
A weather working day counts only working days, or parts of them, on which the weather would allow cargo work. The same number of days gives the charterer more elapsed time on weather working days.
What do SHEX and SHINC mean under GENCON 2022?
GENCON 2022 Clause 10(a) defines both.
SHINC means laytime runs continuously and without interruption for public holidays and customary days of rest at the port, whether or not work is done at overtime rates. SHEX means public holidays and customary days of rest at the port are excluded from laytime unless used. The Laytime Definitions 2013 do not themselves define SHEX or SHINC.
What does 'unless used' mean in a laytime clause?
Under definition 22, if laytime has commenced but loading or discharging is carried out during excepted periods, the actual time used counts as laytime.
It is the default reading of SHEX in GENCON 2022. Without the proviso, definition 19 says excepted days do not count even if work is carried out on them.
What does 'even if used' mean?
It is market shorthand, not a term defined in the Laytime Definitions 2013.
It states expressly what definition 19 already provides for a day described as excepted or excluded: the day does not count as laytime even if cargo is worked on it.
What is turn time or notice time?
It is the interval between a valid notice of readiness and the start of laytime.
The tanker forms fix it at six hours: ASBATANKVOY 1977 Clause 6, SHELLVOY 6 Clause 13(1)(a) and BPVOY4 Clause 7.3.2. GENCON 2022 instead fixes start hours, 14.00 or 08.00 local time, under Clause 11. Definitions 20 and 21 of the Laytime Definitions 2013 deal with cargo work done during turn time.
Does laytime start early if the charterer starts loading during turn time?
Under ‘unless sooner commenced’ (definition 20) laytime commences when loading or discharging begins during turn time.
Under ‘unless sooner commenced, in which case actual time used to count’ (definition 21) only the time actually used counts. GENCON 2022 Clause 11(a) starts laytime at the commencement of cargo operations if that comes first.
Does time spent shifting between berths count?
Under GENCON 2022 Clause 12(a), shifting to a second berth at the same port, or out of and back to the same berth, other than for the owners’ purposes, counts as laytime or time on demurrage.
BPVOY4 Clause 5.3 also counts shifting time, subject to Clauses 17 and 18.2. SHELLVOY 6 Clause 9 counts shifting caused by wind or water conditions.
Does a breakdown of the ship's cargo gear stop laytime?
Under GENCON 2022 Clause 4(c), time actually lost by breakdown of the vessel’s cargo-handling gear or lack of sufficient power does not count as laytime or time on demurrage, unless the charterers’ servants, agents or subcontractors caused or contributed to it.
ASBATANKVOY 1977 Clause 7 similarly excludes delay due to the vessel’s condition or the inability of her facilities to load or discharge within the time allowed.
How do strikes affect laytime under GENCON 2022?
Clause 17 governs. If a strike delays the ship after loading has begun, demurrage is paid at half rate for the first ten cumulative days and at full rate after that.
Once total delay reaches 25 cumulative days, owners get the higher of the demurrage rate and the prevailing market hire rate plus bunkers consumed. Before loading, owners may ask charterers to confirm that laytime counts as if there were no strike, and may cancel if no confirmation comes within 24 hours.
Who has to prove that an exception applies?
The charterer.
In The Ladytramp [2013] EWCA Civ 1449 the Court of Appeal treated the burden as on charterers to show that delay fell within the clause relied on, and held that destruction of a loading plant’s machinery by fire was not, without more, a mechanical breakdown under the clause in that charter.
Does bad weather stop the clock once the ship is on demurrage?
Not unless the charter says so.
Definition 30 of the Laytime Definitions 2013 provides that demurrage is not subject to exceptions which apply to laytime unless specifically stated in the charter party. That is the rule usually summarized as once on demurrage, always on demurrage.
When does laytime end?
When cargo operations are complete as the charter defines completion.
GENCON 2022 Clause 12(c) runs time until completion of cargo operations including removal of stevedores’ equipment, gives charterers three hours at each loading port to provide cargo documents, and restarts time after that until they are received. BPVOY4 Clause 7.3.3 runs time until the cargo hoses are finally disconnected.
How is demurrage calculated from laytime?
Laytime used is totalled from the statement of facts, starting at the charter’s commencement point and deducting excepted periods.
If it exceeds laytime allowed, the excess in days and fractions of a day is multiplied by the demurrage rate. Exceptions stop applying once the ship is on demurrage unless the charter extends them.
What is the difference between reversible and averaged laytime?
Reversible laytime (definition 24) gives the charterer the option to add loading and discharging time together, with the same effect as a single total allowance.
Averaging (definition 23) keeps separate calculations but sets time saved in one operation against excess time used in the other. The two can produce different demurrage figures because demurrage time is not subject to laytime exceptions.
Can reversible laytime be applied between two loading ports?
Not under definition 24 as BIMCO’s commentary explains it.
Reversibility applies between loading and discharging ports, not between loading ports or between discharging ports. A charter wanting another arrangement has to say so expressly.
Is laytime reversible by default under GENCON 2022?
No. Where separate laytime for loading and discharging is agreed in Box 17, GENCON 2022 Clause 10(b)(i) states that laytime for loading and discharging is non-reversible.
A single total allowance under Box 17(iii) and Clause 10(b)(ii) covers both operations.
What is despatch, and how is it paid under GENCON 2022?
Despatch is an agreed amount the owner pays if the vessel completes loading or discharging before laytime expires (definition 31).
GENCON 2022 Clause 13(a) pays it at half the demurrage rate on all laytime saved. Clause 10(a) incorporates the 2013 Definitions, and definition 32 treats all laytime saved as the same thing as all working time saved, so excepted periods after completion are left out.
What is the difference between despatch on all time saved and on working time saved?
Both run from completion to the expiry of laytime.
Despatch on all working time saved, or on all laytime saved, excludes periods excepted from laytime (definition 32). Despatch on all time saved includes them (definition 33), so it produces the larger figure whenever a weekend or holiday falls in the saved period.
What are the statement of facts and the time sheet?
The statement of facts is the record of the ship’s arrival, notice, berthing, cargo work and stoppages, usually prepared by the port agent.
The time sheet applies the charter terms to those facts to arrive at laytime used. BIMCO’s current forms are the Standard Statement of Facts (short form) and the Standard Time Sheet (short form), both of 1975 and recommended by BIMCO and FONASBA.
How is laytime affected if the cargo quantity is short-shipped?
Under GENCON 2022 Clause 10(c), where laytime is calculated on the quantity shipped and charterers pay full freight on a short-shipment, laytime is calculated on the bill of lading quantity plus the short-shipped quantity.
The owner is not penalized in laytime for cargo the charterer failed to supply.
Does laytime run if the charterer has no cargo ready?
The charterer has an absolute obligation to provide the cargo, although it need only have it ready in time to complete loading within the laytime.
In The Nikmary [2003] EWHC 46 (Comm), delay caused by the charterer’s failure to have cargo available was held not to fall within the ASBATANKVOY Clause 6 proviso for delays beyond the charterer’s control.
Who bears the risk of port congestion?
It depends on the clauses. Under a berth charter without a waiting clause, the owner bears waiting time before berthing.
WIBON (definition 27) moves the risk of congestion, but not weather, to the charterer. Under ASBATANKVOY, The Laura Prima [1982] 1 Lloyd’s Rep 1 (HL) held that where charterers had agreed a berth reachable on arrival, congestion delay counted against them; The Notos [1987] 1 Lloyd’s Rep 503 (HL) held that delay from swell, with no reachable-on-arrival undertaking, did not count.
Can the owner claim damages for delay on top of demurrage?
Not for late completion of cargo work alone.
In The Eternal Bliss [2021] EWCA Civ 1712 the Court of Appeal held that demurrage liquidates all the owner’s loss from the charterer’s failure to load or discharge within laytime; unliquidated damages require breach of a separate and distinct obligation. The court endorsed The Bonde, decided by Potter J at first instance in 1991.
How does laytime in a voyage charter differ from time charter hire?
Laytime and demurrage exist only in voyage charters and contracts of affreightment, where the freight pays for the voyage and laytime allocates port time.
Under a time charter the charterer pays hire for all time and the owner’s relief from lost time is through the off-hire clause, so there is no laytime account.
How long does the owner have to present a demurrage claim?
There is no general rule; it is a matter of the charter.
BPVOY4 Clause 20.1 releases charterers unless a written claim with all supporting documentation is presented within 90 days of completion of discharge. In The Eagle Valencia [2010] EWCA Civ 713, the charter’s SHELLVOY 5 Part II Clause 15(3), as amended, set 60 days to notify and 90 days to submit documents.
Does Chinese law have its own laytime rules?
The Maritime Code of the People’s Republic of China 1992 lists laydays, loading and discharging time, demurrage and despatch among the contents of a voyage charter (Article 93) and leaves their calculation and rates to the parties’ agreement (Article 98).
A revised Maritime Code was adopted on 28 October 2025 and took effect on 1 May 2026.
No question matches. Try a shorter or different word.
Sources
- BIMCO, CMI, FONASBA and INTERCARGO. Laytime Definitions for Charter Parties 2013 bimco.org
- FONASBA. Documentation, VOYLAYRULES 2013 jointly issued by BIMCO, CMI, FONASBA and Intercargo fonasba.com
- BIMCO Special Circular No. 8, 10 September 2013. Laytime Definitions for Charter Parties 2013 (VOYLAYRULES 2013) fonasba.com
- BIMCO. GENCON 2022 bimco.org
- BIMCO. Standard Statement of Facts (short form), 1975 bimco.org
- BIMCO. Standard Time Sheet (short form), 1975 bimco.org
- K Line Pte Ltd v Priminds Shipping (HK) Co Ltd (The Eternal Bliss) [2021] EWCA Civ 1712 caselaw.nationalarchives.gov.uk
- K Line Pte Ltd v Priminds Shipping (HK) Co Ltd (The Eternal Bliss) [2020] EWHC 2373 (Comm) caselaw.nationalarchives.gov.uk
- Triton Navigation Ltd v Vitol SA (The Nikmary) [2003] EWHC 46 (Comm) caselaw.nationalarchives.gov.uk
- CM P-Max III Ltd v Petroleos del Norte SA (The Stena Primorsk) [2022] EWHC 2147 (Comm) caselaw.nationalarchives.gov.uk
- National Shipping Co of Saudi Arabia v BP Oil Supply Co (The Abqaiq) [2011] EWCA Civ 1127 caselaw.nationalarchives.gov.uk
- ED&F Man Sugar Ltd v Unicargo Transportgesellschaft mbH (The Ladytramp) [2013] EWCA Civ 1449 caselaw.nationalarchives.gov.uk