NEWBUILDCON is BIMCO’s standard shipbuilding contract, issued in 2007 and still the only edition. BIMCO describes it as the industry’s only international standard shipbuilding contract, drafted for use in any jurisdiction and for any ship type, and written to sit more evenly between builder and buyer than the older yard forms.

It prescribes no instalment split. Clause 15 makes instalments fall due in accordance with Box 11, which the parties complete, so the familiar five-payment structure is market practice rather than anything the form imposes. What the form does fix is that pre-delivery instalments are advances, not deposits, which shapes what the buyer can recover if the yard fails.

Clause 16 carries a matched pair of securities: the Instalment Guarantee in the builder’s favour, form at Annex A(ii) with the bank named in Box 31, and the refund guarantee in the buyer’s favour, form at Annex A(iii) with the bank named in Box 32.

The full article will cover the Part I box layout, the specification and inspection regime, delivery and performance warranties, the Clause 39 termination grounds on both sides, and how NEWBUILDCON compares with the Shipbuilders’ Association of Japan form and the CMAC Shanghai Form.