Offshore Cranes and Heavy Lifting

Offshore cranes and heavy lifting: API Spec 2C dynamic coefficients, EN 13852 and DNV crane standards, splash-zone loads, rigging, IMCA lift categories and MWS.

Contents17 sections

An offshore crane is a slewing crane mounted on a fixed platform, a floating installation or a vessel and rated to transfer loads in a seaway, and offshore heavy lifting is the wider practice of installing modules, jackets, topsides and subsea structures with those cranes and with purpose-built crane vessels. The governing problem is that the load the crane carries is not the weight on the data plate. API Spec 2C, the American Petroleum Institute’s specification for offshore pedestal-mounted cranes, multiplies the safe working load by a vertical dynamic coefficient of not less than 1.33 for a crane on a fixed platform and 1.40 for one on a floating platform or vessel (6th edition, March 2004, Eq. 4.1), and a lift through the sea surface adds slamming, buoyancy and snap loads on top. Design standards (API Spec 2C, EN 13852-1:2025, DNV-ST-0378), national regulations (30 CFR 250.108 in the United States, the Norwegian Maritime Authority’s 2017 crane regulation, the UK’s LOLER 1998), marine-operations standards (DNV-ST-N001 Edition 2023-12, DNV-RP-N103) and the IMCA lifting guidelines (IMCA M 187 Rev. 2.1, June 2023) each control a different link in that chain.

The boundary with merchant cargo work runs through the duty, not the machine. Cranes carried to work a ship’s own cargo are certified under SOLAS regulation II-1/3-13 and covered at ship cargo gear: cranes, derricks and lifting appliances. This article covers the offshore lift: the crane on the installation or the construction vessel, the dynamic loads that derate it, the rigging, the planning categories and the survey regime. The installation campaigns those lifts serve are covered at subsea, pipelay and offshore installation.

Offshore cranes, crane vessels and heavy-lift equipment

Offshore lifting equipment falls into two families, and the difference is where the lifting capacity comes from. A pedestal crane takes its capacity from its own steel and from the column and deck it stands on. A crane vessel takes it from the buoyancy and ballast of a hull, which is how a single hook reaches into the thousands of tonnes.

Pedestal cranes on platforms, FPSOs and vessels

A pedestal crane is a slewing crane on a fixed column, the pedestal, welded to the deck of a fixed platform, a jack-up, a semisubmersible drilling unit, an FPSO or a vessel. API Spec 2C defines offshore cranes as pedestal-mounted elevating and rotating lift devices used to transfer materials or personnel to or from marine vessels and structures, and its 6th edition lists tension-leg platforms, spars, semisubmersibles, drillships and FPSOs as the floating platforms whose cranes take the higher dynamic coefficients. The everyday work is the supply-boat lift: stores, chemicals and equipment lifted off the deck of an offshore supply vessel heaving alongside.

The pedestal carries the whole overturning moment of the lift into the structure, and the slewing bearing between the crane and the pedestal transmits it. That moment, not the hook capacity alone, often sets the limit of a platform crane, because the deck steel beneath was sized for a stated moment when the platform was designed. Duty classification under the ISO and FEM schemes is covered at crane classification and duty groups, and limit switches, rated-capacity indicators and the anti-two-block device at crane overload protection and safety devices.

Sheerlegs, monohull crane vessels and semi-submersible crane vessels

A sheerleg is a rigid A-frame raked over the bow of a pontoon, with the hook hanging from the apex. The frame does not slew, so the load is positioned by moving the whole hull, which suits harbor, nearshore and sheltered-water lifts. A monohull crane vessel puts a revolving crane on a ship-shaped hull with dynamic positioning, as on DEME’s Orion, an offshore heavy-lift DP3 installation vessel with a 5,000 t main crane and a 1,500 t auxiliary crane. Monohull and jack-up crane units are the workhorses of offshore wind foundation and turbine installation, covered at wind turbine installation vessels.

A semi-submersible crane vessel (SSCV) floats on submerged pontoons joined to the deck by columns. The small waterplane area makes its response to waves in heave, roll and pitch much gentler than a barge’s, the subject of seakeeping, and that is what lets it lift in open-sea conditions that weather-bind a barge crane.

VesselOperatorTypeLifting capacity stated by the operator
SleipnirHeerema Marine ContractorsSemi-submersible crane vesselTwo 10,000 t cranes; up to 20,000 t in tandem; 15,300 t Leviathan topside, September 2019
ThialfHeerema Marine ContractorsSemi-submersible crane vessel14,200 t lift capacity
OrionDEMEMonohull DP3 heavy-lift installation vessel5,000 t main crane, 1,500 t auxiliary crane
Pioneering SpiritAllseasTwin-hull single-lift vesselTopsides lift system up to 60,000 t; jacket lift system up to 20,000 t; 5,000 t special-purpose crane at 35 m radius

Two errors recur when these figures are quoted. Sleipnir’s 20,000 t is a two-crane tandem figure, not a per-crane rating, and Thialf’s 14,200 t is the vessel lift capacity Heerema states, with no per-crane figure; the largest single offshore crane in the table is one of Sleipnir’s at 10,000 t. And Pioneering Spirit’s 60,000 t and 20,000 t figures belong to its dedicated topsides and jacket lift systems at the bow and stern, while its own special-purpose crane is rated 5,000 t at 35 m, so the vessel competes with crane vessels by a different method.

Where SOLAS regulation II-1/3-13 stops

SOLAS regulation II-1/3-13, inserted by resolution MSC.532(107) of 8 June 2023 and in force from 1 January 2026, brought lifting appliances and anchor-handling winches on SOLAS ships into the convention. It reaches the deck crane on a supply vessel and, through the definition in regulation II-1/2.30, personnel-handling cranes. Paragraph 1.2 then excludes two groups that matter offshore: lifting appliances on ships certified as mobile offshore drilling units, and appliances on offshore construction ships engaged in pipe or cable laying, repair, offshore installation or decommissioning, where they comply with standards acceptable to the Administration. MODU cranes stay with the MODU Code; construction-ship cranes stay with the standards the flag Administration accepts, usually class rules; and the coastal State adds its own regime on its continental shelf. The regulation and its guidelines in MSC.1/Circ.1663 are covered at SOLAS regulation II-1/3-13.

Standards and regulations for offshore cranes

Offshore crane design is governed by industry and class standards, and offshore crane use by national law. SOLAS applies to ships, so a crane on a fixed platform sits under the law of the coastal State whose continental shelf the platform stands on, which then names a standard.

InstrumentBodyWhat it coversEdition or status
API Spec 2CAmerican Petroleum InstituteDesign, rating and dynamic coefficients of offshore pedestal cranes; 8th edition extends to shipboard cranes8th edition, Errata 1 (2021), reaffirmed 2025; US law incorporates the 6th (2004)
API RP 2DAmerican Petroleum InstituteOperation, inspection, maintenance and personnel qualification for offshore cranes7th edition; US law incorporates the 6th (2007)
EN 13852-1CENGeneral-purpose offshore cranes2025 edition (April 2025), superseding 2013
EN 13852-2 and EN 13852-3CENFloating cranes; light offshore cranes2014; 2021
DNV-ST-0378DNVOffshore and platform lifting appliances, class certificationJuly 2019, amended October 2021
DNV-ST-0377DNVShipboard lifting appliancesFebruary 2022
LR Code for Lifting Appliances in a Marine EnvironmentLloyd’s RegisterLifting appliance certificationCode Notice No. 2, July 2024
ABS Guide for Certification of Lifting AppliancesABSLifting appliance certification and notationsAugust 2024
BV NR526Bureau VeritasLifting appliance rules, including offshore liftingJanuary 2026
DNV-ST-N001DNVMarine operations and marine warranty, including liftingEdition 2023-12
DNV-RP-N103DNVModelling and analysis of marine operations, including lifts through the wave zone2017-07, amended 2021-09
IMCA M 187IMCAGuidelines for lifting operationsRev. 2.1, June 2023
ISO 4309:2017ISOWire rope care, inspection and discardCurrent; revision under way

A crane can carry several of these at once: an EN 13852-1 design for its CE marking, a DNV-ST-0378 or ABS certificate from its classification society, and an API Spec 2C rating because the buyer’s field sits in US waters. Lloyd’s Register and Bureau Veritas publish their own lifting-appliance rules, and DNV holds both the crane standard and the marine-operations standard.

United States: 30 CFR 250.108 and the API editions

30 CFR 250.108 requires every crane installed on a fixed platform on the US Outer Continental Shelf to be operated in accordance with API RP 2D. API Spec 2C applies to all cranes on a fixed platform installed after 17 March 2003, and to every crane manufactured after that date and installed on a fixed platform. Each crane must carry a functional anti-two-block device, the switch that stops the hook block being hoisted into the boom tip. Under paragraph (e), design and construction records stay at the platform for the life of the crane, and inspection, testing and maintenance records and the qualification records of the crane operator and every rigger for at least 4 years.

The incorporated editions are older than the current ones. 30 CFR 250.198 incorporates API Spec 2C 6th edition (March 2004) and API RP 2D 6th edition (May 2007). The Bureau of Safety and Environmental Enforcement proposed moving to Spec 2C 8th edition and RP 2D 7th edition. Its final incorporation-by-reference rule, 91 FR 35304, published on 10 June 2026 and effective 10 August 2026, left them out: BSEE had not proposed how existing cranes would comply with the newer editions, and stated it will repropose them. The section covers fixed platforms; cranes on floating facilities and vessels are under US Coast Guard rules. BSEE’s wider management-system rule is covered at BSEE SEMS, and the standard itself at API Spec 2C and API RP 2D.

Norway: NMA Regulations 2017 No. 2381 and NORSOK

The Norwegian Maritime Authority’s Regulations of 21 December 2017 No. 2381 on cranes and lifting operations on mobile offshore units entered into force on 1 January 2018, were amended in 2022 (No. 118) and 2023 (No. 459), and apply to Norwegian mobile offshore units. Section 8 requires offshore cranes to reach the safety level of EN 13852-1:2013 or DNVGL-ST-0378 (May 2016), or an equivalent standard of another MOU classification society. The regulation still names those editions, not EN 13852-1:2025 or the 2019 DNV-ST-0378.

Loose lifting equipment follows NORSOK R-002 Edition 3 (March 2017), Annexes C and F; use of cranes and loose gear follows NORSOK R-003 Edition 3 (June 2017), Chapters 5 to 7; and wire rope use, servicing and replacement follow NS-ISO 4309:2010. Certificates are issued on ILO Form No. 2 for cranes, No. 3 for loose gear and No. 4 for wire rope forms also used under ILO Convention 152, which fill a register of lifting appliances. The personnel-lifting provisions are set out in the section on lifting personnel below.

United Kingdom: LOLER

The Lifting Operations and Lifting Equipment Regulations 1998, SI 1998/2307, set the UK’s thorough-examination regime. HSE guidance on LOLER gives intervals of 6 months for lifting accessories and for lifting equipment used to lift people, and 12 months for all other lifting equipment, unless an examination scheme drawn up by a competent person sets other intervals. Regulations 9, 10 and 11 carry the examination, reporting and record-keeping duties.

Crane rating, the dynamic coefficient and sea state

An offshore crane’s rating is conditional on the motion of the crane and of the load, so one crane carries several load charts. API Spec 2C ties each load chart to the significant wave height, Hsig, associated with it (6th edition, definition 3.1.51), and the crane’s vertical design load is the safe working load multiplied by the vertical dynamic coefficient Cv (3.1.33). A higher sea state raises Cv, and for a structure of fixed strength a higher Cv lowers the load the chart allows. A lift planned against the still-water chart and carried out in a seaway can overload the crane.

API Spec 2C offboard lifts

For an offboard lift, a load picked up from or set down on a supply vessel, the 6th edition of API Spec 2C sets the dynamic coefficient by Eq. 4.1:

$$ C_v = 1 + V_r \sqrt{\frac{K}{g \cdot SWL}} $$

where \( K \) is the vertical spring rate of the crane at the hook in lb/ft, worked through every element from the hook to the pedestal, \( SWL \) is the safe working load in lb, \( g \) is 32.2 ft/s squared, and \( V_r \) is the relative velocity in ft/s between the hook and the load:

$$ V_r = V_h + \sqrt{V_d^2 + V_c^2} $$

with \( V_h \) the maximum steady hoisting velocity, \( V_d \) the vertical velocity of the supply-boat deck and \( V_c \) the vertical velocity of the boom tip from the motion of the crane’s own base. The result is not less than 1.33 for a fixed-platform crane or 1.40 for a crane on a floating platform or vessel. Because the SWL appears on both sides, the rating is found by iteration. Table 2 gives the deck velocity: zero for a fixed structure, \( V_d = 0.6 H_{sig} \) for a moving vessel below a 9.8 ft (about 3.0 m) significant wave height, and \( V_d = 5.9 + 0.3 (H_{sig} - 9.8) \) above it, all in feet and feet per second. The coefficients are unit-specific, so a calculation done in meters has to convert Hsig before applying them.

Physically, Eq. 4.1 treats the load as a mass on a spring struck at a closing speed. A stiffer crane (higher K) or a lighter load raises Cv, which is why a small load on a large crane can see a higher dynamic coefficient than a heavy one. A faster hoist reduces the time the load spends near the heaving deck but adds directly to the closing speed.

Appendix E.1 of the 6th edition works the method for a drillship crane lifting 20,000 lb at a 100 ft radius from a supply boat in a 6.6 ft significant wave height. With K of 24,000 lb/ft, a hoisting speed of 100 ft/min (1.67 ft/s), a deck velocity of 0.6 x 6.6 = 3.96 ft/s and a boom-tip velocity of 2.18 ft/s, the relative velocity is 6.19 ft/s and Cv is 2.195, so the vertical design load is about 43,900 lb. That is well above the 1.40 floor, which is a minimum, not a typical offboard value.

Onboard lifts and the vessel type

For onboard lifts, where the crane moves a load around its own installation, the deck and boom-tip velocity terms are taken as zero and the coefficient comes from the motion of the installation. Under the Vessel Specific Method, Cv is 1.33 plus the vertical boom-tip acceleration, in g, from a motion analysis. The General Method in Table 3 gives a formula by installation type, with Hsig in feet:

InstallationOnboard Cv (API Spec 2C 6th ed., Table 3)At Hsig 20 ft (about 6.1 m)
Fixed structure1.331.33
TLP or spar1.33 + 0.003 Hsig, not less than 1.41.40 (1.39 calculated, floor applies)
Semisubmersible1.33 + 0.0007 Hsig squared, not less than 1.41.61
Drillship or FPSO1.33 + 0.0012 Hsig squared, not less than 1.41.81

The ordering follows the ship motions of each hull form. A tethered TLP barely heaves, so its coefficient grows linearly and slowly; a ship-shaped FPSO pitches and rolls, so its coefficient grows with the square of the wave height.

The Default Dynamic Method and minimum hoisting speed

The 6th edition allows a flat Cv of 2.0 for offboard lifts only under the Default Dynamic Method. That method is limited to fixed platforms in mild sea and wind conditions, with the Gulf of Mexico as the stated example, and to cases where the supply vessel’s position is held constant relative to the platform, such as a platform-tethered supply vessel. Offlead and wind may then be taken as zero and the sideload is 2 percent of the vertical design load, 0.02 x 2.0 x SWL. Onboard lifts under the same method take 1.33.

Eq. 4.2 sets a minimum steady hoisting velocity, unless otherwise agreed with the purchaser, of \( V_{h,min} = 0.1 (H_{sig} + 3.3) \) ft/s with Hsig in feet. Its purpose is to lift the load clear of the supply-boat deck before the next crest brings the deck back up into it. At a 6.6 ft (2 m) significant wave height the minimum is 0.99 ft/s, about 0.30 m/s.

These are 6th-edition figures, quoted because 30 CFR 250.198 incorporates that edition. A crane certified to the 8th edition, to EN 13852-1:2025 or to DNV-ST-0378 is rated by that document’s method, and its values are taken from that document.

Pedestal overturning moment

The load moment a lift drives into the pedestal is the safe working load times the radius times the dynamic coefficient. API Spec 2C 6th edition (9.2.1.1) calculates the swing-circle overturning moment and the axial and radial loads from the maximum SWL times Cv plus dead load, and checks ultimate strength at dead load plus 3.75 times the maximum SWL times Cv (9.2.1.4). A 50 t load at a 25 m radius gives a static load moment of 1,250 t-m; at a Cv of 1.4 the design moment is 1,750 t-m, before the self-weight of the boom is added. The moment rises linearly with radius, so a load that is within the chart at 15 m can exceed the pedestal’s capacity at 25 m.

DNV-ST-0378

Overturning Moment

$$M = SWL \cdot r \cdot \psi$$

where

\(M\)Overturning moment at the pedestalt·m
\(SWL\)Safe working load on the hookt
\(r\)Lift radius (slew center to hook)m
\(\psi\)Dynamic coefficient (API Spec 2C Cv, or the DAF of the governing standard)

Dynamic amplification factor and the design hook load

The dynamic amplification factor is the multiplier the lifting engineer applies to the static weight of a lifted object and its rigging to get the peak load of a specific lift. IMCA M 187 writes the dynamic hook load as DHL = DAF x (weight of object + weight of rigging) + additional hook loads, such as the pull of tugger lines and guide wires. Every item downstream, the hoist rope, the slings, the shackles, the spreader bar, the padeyes and the pedestal, is checked against that dynamic load, not the static weight. The concept and its variants across standards are covered at dynamic amplification factor.

Crane coefficient against lift DAF

The API Spec 2C coefficient and a lift DAF are easily confused. Cv is a crane-design quantity: the manufacturer designs the crane’s structure and rope system for SWL x Cv at the sea state of each chart. A lift DAF is a lift-design quantity: it describes the dynamic response of one object on one rigging arrangement in one sea state, from the in-air lift-off through to landing. A crane built for Cv 1.4 does not license a lift at a DAF of 1.4; the lift has to fit inside the chart issued for the operation’s sea state, and its own DAF governs the rigging. Marine-operations standards such as DNV-ST-N001 set lift DAFs, and the project’s lifting specification names the values used.

The load chain

The design load is a chain of factors, each covering a different uncertainty, and the factors multiply. The order a lifting specification usually follows is:

  1. The gross weight of the object, weighed or calculated, with a weight-contingency factor while it is calculated rather than weighed.
  2. A center-of-gravity factor for the uncertainty in where the weight acts, since an offset center of gravity moves load between slings.
  3. The DAF for motion and acceleration.
  4. A skew-load factor for uneven load sharing in a statically indeterminate rigging arrangement such as four slings on four padeyes.
  5. A consequence factor on the components whose failure would drop the load, which raises their required strength.

Illustrative arithmetic, with values chosen only to show the compounding: a 100 t object with a 1.05 contingency, a 1.08 center-of-gravity factor and a 1.30 DAF gives 100 x 1.05 x 1.08 x 1.30 = 147.4 t of design hook load, before skew and consequence factors. The values for an actual lift come from the governing standard and the lifting specification, never from a generic table. Under IMCA M 187, rigging design calculations of this kind belong to the engineered-lift plan prepared by an onshore engineering organization.

Where the DAF comes from physically

The DAF is the response of a mass on a spring driven by the motion of the crane tip. The wire is the spring, the object is the mass, and the vessel’s heave, roll and pitch move the tip. When the driving period approaches the natural period of the wire-and-load system, the response amplifies. Paying out more wire softens the spring and lengthens the natural period, so a load on 1,000 m of wire responds differently from the same load on 20 m. That is why an engineered subsea lift models the wire stiffness, the load’s mass and added mass, and the vessel’s response amplitude operators together, rather than reading a DAF off a table.

Moving base, weather window and limiting criteria

Every offshore lift plan states limiting criteria, typically a maximum significant wave height, a maximum wind speed and, for subsea work, current and swell limits. The operation starts only inside a forecast window long enough for the planned duration plus a contingency. A lift that takes 8 hours needs a window longer than 8 hours with margin, because a window that closes mid-lift can leave a partly landed module in a rising sea.

The crane chart, the DAF and the window are linked. A lower wave-height limit gives a lower dynamic coefficient and a higher allowable load, so a project trades lifting capacity against waiting time. Long-term wave statistics for a site are expressed as a wave scatter diagram, and the expected downtime as weather working days. The person in charge of the lift, and on a mobile unit the offshore installation manager, stops the operation when the measured conditions leave the limits, whatever the forecast said. Vessel motion is monitored during the lift by a motion reference unit, the same sensor that feeds the DP system and any heave compensator.

As the hook takes the weight off a heaving supply-boat deck, a downward deck motion snatches the load onto the wire, and an upward motion can bring the deck back up into a load that has only just cleared. That re-contact is what the API Spec 2C minimum hoisting speed exists to prevent.

Splash zone: slamming, buoyancy and snap loads

The splash zone is the band near the sea surface where a lowered object is partly in and partly out of the water and wave action is strongest, and its crossing is usually the governing case of a subsea lift. As the object enters the water the rising face of a wave strikes it with a slamming force that grows with the square of the relative velocity between the water surface and the object. As it submerges, buoyancy reduces the net weight on the wire, added mass increases the inertia the wire must accelerate, and drag resists vertical motion. DNV-RP-N103, Modelling and analysis of marine operations (Edition 2017-07, amended 2021-09), gives simplified formulations for these design loads for planning and executing marine operations, including lifts through the wave zone. The mechanics are covered at splash zone lifting and snap loads.

The hazard is the reversal. While the object is in the splash zone the wire tension swings between a high value at slam and a low one as buoyancy and an upward wave lift the object. If the water lifts the object faster than the wire pays out, the wire goes slack. When the water drops away, the object falls back onto the slack wire and snatches it tight. That snap load can exceed the rating of the wire or the rigging and drop the object.

Crossing the splash zone

The defenses all control the relative velocity between the object and the water:

  • crossing the surface quickly and at a wave trough, to limit the number of wave cycles the object spends in the zone;
  • an active heave compensation system on the crane or winch, which pays out and hauls in against the measured vessel motion so the load tracks the water and the wire stays in tension;
  • venting the object, with holes and flow paths that reduce trapped-water slamming and added mass;
  • setting the limiting sea state from an analysis whose acceptance criteria are that the minimum wire tension stays positive and the maximum stays below the rating.

EN 13852-1:2025 leaves cranes with 2D or 3D motion compensation outside its scope, so a motion-compensated crane is certified against another document.

Landing on the seabed

Below the surface the wave effects fade with depth and the wire tension settles toward the object’s submerged weight, but the lift is not over. The landing is a controlled load transfer from the wire to the seabed or to a pre-installed structure, guided by a remotely operated vehicle or, in shallower water, by divers working from a dive support vessel. For deep lifts the wire’s own weight becomes a large share of the hook load, which is one reason deepwater installation uses fiber rope or staged lowering. The installation campaigns that run these lifts, from pipelay vessels to construction vessels, are covered at offshore support vessels and marine operations.

Rigging: slings, shackles, spreader bars and wire rope

Rigging is everything between the hook and the object, and it is sized against the design load, not the static weight. The accessories are wire-rope, chain and fiber slings, shackles, master links, spreader bars and lifting frames, covered at chain slings and rigging hardware and spreader bars and lifting frames. Each carries a working load limit and a minimum breaking load, and the ratio between them is its design factor. Proof loading and the relationship between proof load and working load are covered at safe working load and proof load testing. Heavy lifts above the range of single-laid slings use cable-laid slings and grommets, made and used to IMCA M 179 (LR 008), Rev. 2 of April 2025, and covered at cable-laid slings and grommets; high-performance fiber slings for engineered lifts follow IMCA M 237 (LR 009), Rev. 1.1 of February 2024.

Sling angle

A multi-leg sling shares the load equally between its legs only when they hang vertically. Each leg carries its share of the vertical load divided by the cosine of its angle \( \theta \) from vertical:

$$ T_{leg} = \frac{W}{n \cos\theta} $$

for \( n \) equally loaded legs carrying weight \( W \). At 45 degrees the factor \( 1/\cos\theta \) is 1.41; at 60 degrees it is 2.0, so a two-leg sling at 60 degrees puts the full weight of the object into each leg. A spreader bar holds the legs near vertical and keeps the factor close to 1.0, at the cost of its own weight and a buckling check on the bar in compression. A four-leg sling on four padeyes is statically indeterminate, and small differences in sling length or padeye position can put most of the load on two diagonally opposite legs, which is what the skew-load factor covers.

Wire rope design factors and discard

API Spec 2C 6th edition sets the hoist rope design factor at not less than 2.5 x Cv or 5.0, whichever is greater (7.2.4.1), and standing ropes such as boom pendants at not less than 2.0 x Cv or 4.0, whichever is greater (7.2.4.2). Up to Cv 2.0 the fixed minimum of 5.0 governs the hoist rope; a crane with Cv 2.4 needs 6.0. When the crane handles personnel the hoist rope design factor is not less than 10 (7.2.4.3). Construction and selection of the rope itself is covered at steel wire rope construction and selection, and the end fittings at wire rope terminations.

Discard follows ISO 4309:2017, Cranes: Wire ropes: Care and maintenance, inspection and discard, which counts visible broken wires over lengths of 6 and 30 rope diameters, with a revision under way; the method is covered at wire rope inspection and discard. The Norwegian MOU regulation still names NS-ISO 4309:2010. Offshore rope integrity programs run under IMCA M 194, Rev. 4 of October 2023, and magnetic rope testing under IMCA M 197, Rev. 2 of July 2024.

Certification, marking and examination

Every accessory carries an identification mark and its working load limit, and goes on the hook only with a current certificate and a recorded thorough examination. In the UK the LOLER intervals apply: 6 months for accessories, 12 months for other lifting equipment, or an examination scheme. On a Norwegian mobile unit the certificates use the ILO forms and loose gear is used, examined and stored to NORSOK R-003 Edition 3, Chapter 7. A rigging loft keeps the register: each item’s identity, working load limit, last examination and proof-test record. ISO 2415:2022 covers forged shackles, ISO 16855 to 16858:2013 marine loose gear, and ISO 19354:2016 marine cranes.

Padeyes and trunnions

The lift points are part of the lift design. A padeye is a plate with a hole welded to the structure to take a shackle pin; a trunnion is a stub shaft the sling bears on. They are placed so the slings clear the structure, so the resultant of the leg tensions passes through the center of gravity or holds a planned tilt, and so the local steel carries the design sling load, including the out-of-plane component when a sling does not pull in the plane of the padeye.

Lift planning and the IMCA lift categories

IMCA M 187, Guidelines for lifting operations, also numbered D 060, HSS 019 and LR 006 across the International Marine Contractors Association’s technical divisions, is current at Rev. 2.1, issued June 2023 after a technical revision in August 2022. Rev. 1 (March 2018) identifies three categories of lift, and every lift, whatever its category, needs a lift plan. Where the category is in doubt, the lift is treated as non-routine. The table follows the Rev. 1 definitions.

CategoryWhat it coversPlan and approval
RoutineRepetitive lifts with common characteristics whose significant elements are unlikely to change, done by a trained team familiar with the taskOne generic routine lift plan by a competent person, supported by a job risk assessment; the lift path need not be defined
Non-routineAny lift that does not meet every routine criterion, or for which no routine plan exists; all lifting of personnel except divers in a compliant launch and recovery systemSpecific lift plan by a competent person, reviewed and approved by another competent person; risk assessment; pre-lift meeting or toolbox talk; lift path defined
EngineeredLifts that need detailed engineeringPlan by an onshore engineering organization to established standards: structural assessment, dimensional checks, rigging calculations, environmental limits, drawings, and vessel stability on sudden loss of hook load where counter-ballasting is used

The category structure puts engineering effort where the consequence is. A basket of stores off a supply boat runs on the generic plan. A blind lift over live process equipment needs its own plan and a pre-lift meeting. A subsea manifold through the splash zone, a jacket, or a tandem lift between two vessels would normally be planned as engineered. On the installation the lift sits inside the offshore permit-to-work system, and the hand signals and lift-plan content are covered at lift planning and crane hand signals.

Roles around the lift

Each lift has named roles. The person in charge of the lift plans and controls it and holds the authority to stop it. The crane operator runs the crane within the chart. The banksman or signaller directs the operator when the load is out of sight. The rigger attaches and detaches the rigging and checks the accessories before use. On an engineered lift a lifting engineer owns the analysis and the rigging design. 30 CFR 250.108(e) requires a US OCS platform to keep the qualification records of the crane operator and every rigger for at least 4 years, and crane operator competence schemes are covered at offshore crane operator certification.

Lifting personnel by crane

Lifting people by crane is a non-routine lift under IMCA M 187 and is restricted under API Spec 2C, the NMA regulation and IMCA guidance. Under API Spec 2C 6th edition (4.1.2), a crane’s personnel rating is the least of 33 percent of its calculated non-personnel safe working load, the load the reeving and rope design factor allow, and the available line pull, and the hoist rope design factor rises to 10.

Norway sets conditions in law. Under section 25 of the NMA Regulations 2017 No. 2381, personnel lifting uses only cranes and lifting appliances certified for it. Transfer of personnel to and from a mobile unit takes place only when warranted by special circumstances, with the offshore installation manager’s approval in consultation with the safety representatives. It stays within the weather restrictions on the certificates or, where none are stated, NS-EN 13852-1:2013 paragraph 7.2.5. Section 8(2) requires a personnel-rated offshore crane to have an emergency operation system available within one minute.

IMCA M 202 (HSS 025, LR 012), Guidance on the transfer of personnel to and from offshore vessels and structures, Rev. 2.2 of March 2024, is the industry guidance. Transfer by motion-compensated gangway, the main alternative to the crane basket on offshore wind and accommodation work, follows IMCA M 254, Rev. 1 of August 2025, covered at walk-to-work operations. The basket transfer is covered at personnel transfer by crane.

Dual-crane and tandem lifts

A tandem lift uses two cranes on one load, because the load is too heavy for one hook or too long to hang stably from one point. The capacities do not simply add. The load shares between the hooks by geometry, and any difference in hoist speed, any tilt of the load or any relative motion moves load from one crane to the other, so one crane can be overloaded while the other is within its chart. The plan models the load share through the expected range of tilt, sets each crane’s limit with headroom for that shift, and synchronizes the hoists; the method is covered at tandem lift operations.

On a semi-submersible crane vessel the two cranes share one hull, which is how Sleipnir’s two 10,000 t cranes lift up to 20,000 t together. A tandem lift between two separate vessels is harder, because the hulls move independently and their relative motion feeds straight into the load share; the vessels’ station keeping and motion response become governing inputs.

Float-over installation compared with a crane lift

A topside is installed by float-over rather than lifted when it exceeds the capacity of the crane vessels available for the campaign, or when a float-over is the cheaper or better-suited option at the site. Weight alone does not force the choice: Heerema’s Sleipnir lifted the 15,300 t Leviathan topside in September 2019, and Allseas rates Pioneering Spirit for topsides of up to 60,000 t in a single lift.

In a float-over installation a barge or vessel carries the integrated topside into a slot in the substructure, a jacket or a gravity-base structure, so the topside’s legs sit over the substructure’s mating points. The vessel is then ballasted down, often on a falling tide, and the weight transfers through leg-mating units on the substructure that guide and cushion the topside, while deck-support units on the vessel release it. The limiting criterion is the relative motion between the floating vessel and the fixed substructure inside the slot, which turns a dynamic-lift problem into a ballast and motion problem governed by the vessel’s intact stability through the transfer. Removal in reverse is part of offshore installation decommissioning.

Marine warranty survey of a lift

A marine warranty survey is an independent review of a marine operation, required where the project’s insurance carries a warranty that the operation be approved by a named surveyor, and it applies to heavy lifts as to tows and load-outs. DNV-ST-N001, Marine operations and marine warranty, Edition 2023-12, covers marine operations during the development or decommissioning of an offshore asset and sets marine warranty survey requirements for load-out, construction afloat, voyages and installation or removal. Its 2020 edition described it as including the harmonized legacy DNV standards and the legacy GL Noble Denton guidelines. Location approval for mobile offshore units sits in DNV-ST-N002.

The surveyor reviews the engineering of a lift: the weights and center of gravity, the DAF and the other factors, the rigging calculations and certificates, the crane’s suitability for the radius and sea state, the weather criteria and forecast, and the procedure. The surveyor then attends to confirm the limiting criteria are met before the operation proceeds. The survey approves the operation, not the hardware: the crane’s certification remains with its class society and, where applicable, the flag State. Contract allocation of the risk of a dropped load between the contractor and the company usually follows knock-for-knock indemnity, and the survey regime is covered at marine warranty survey and DNV-ST-N001.

Common errors in reading offshore crane figures

Four mistakes recur in specifications, tender documents and published summaries:

  • Quoting a tandem total as a crane rating. Thialf’s 14,200 t is a vessel lift capacity; the largest single crane in the operator figures above is one of Sleipnir’s two at 10,000 t.
  • Treating Cv as a DAF. The API Spec 2C coefficient designs the crane; the lift DAF designs the rigging and the operation.
  • Citing the current API edition for US compliance. The current Spec 2C is the 8th edition, but 30 CFR 250.198 still incorporates the 6th (2004), and the June 2026 BSEE rule did not change that.
  • Applying SOLAS II-1/3-13 to every offshore crane. Paragraph 1.2 excludes MODU-certified ships and offshore construction ships whose appliances meet standards acceptable to the Administration.

Limitations

This article sets out the structure of offshore crane rating and lift engineering; it does not replace the governing standard, the crane’s certified load charts, the project lifting specification, or the judgment of a qualified lifting engineer, a competent person and a marine warranty surveyor for a specific operation. The API Spec 2C formulas and coefficients quoted are from the 6th edition (March 2004), the edition 30 CFR 250.198 incorporates; the 8th edition, EN 13852-1:2025 and DNV-ST-0378 use their own methods and values, and a crane is rated only by the document it was certified to. The lift-chain arithmetic uses illustrative values. DNV-ST-N001’s lifting factors are not reproduced, and a lift is designed with the values from the edition named in the project specification. The IMCA category descriptions follow the structure of IMCA M 187, whose current Rev. 2.1 text is available to members; each contractor’s lifting procedures set their own boundaries. Norway’s NMA regulation covers mobile offshore units only, and the US section covers fixed platforms on the Outer Continental Shelf only. The ShipCalculators.com pedestal-moment tool linked from the formula card gives the load moment only and does not replace a structural check of the pedestal and deck.

Frequently Asked Questions (FAQs)

What is the dynamic amplification factor in an offshore lift?

The dynamic amplification factor (DAF) is the multiplier that turns the static weight of a lifted object and its rigging into the peak load the crane and rigging carry once vessel motion, hoisting acceleration and, in the water, hydrodynamic forces are counted.

IMCA M 187, Guidelines for lifting operations, writes the dynamic hook load as DHL = DAF x (weight of object + weight of rigging) + additional hook loads such as tugger-line and guide-wire loads. A DAF of 1.3 on a 100 t object means the hook sees about 130 t before any other factor is applied.

Is the API Spec 2C dynamic coefficient the same thing as a lift DAF?

No. The API Spec 2C vertical dynamic coefficient Cv is a crane-design figure: the crane’s structure is designed for its safe working load multiplied by Cv.

A lift DAF is a lift-design figure applied by the lifting engineer to a specific object, rigging arrangement and sea state. The two are related through the same physics, but a crane designed with Cv 1.4 is not thereby cleared to lift any object at a DAF of 1.4; the lift has to fit inside the load chart issued for the sea state of the operation.

What minimum dynamic coefficient does API Spec 2C set?

For offboard lifts, the 6th edition (March 2004) of API Spec 2C, which is the edition 30 CFR 250.198 still incorporates, sets Cv = 1 + Vr x sqrt(K / (g x SWL)) but not less than 1.33 for a crane on a fixed platform or 1.40 for a crane on a floating platform or vessel.

Vr is the relative velocity between hook and load, combining the hoisting speed with the supply-boat deck velocity and the boom-tip velocity, and K is the vertical spring rate of the crane at the hook.

How does API Spec 2C treat onboard lifts on a floating installation?

For onboard lifts the supply-boat and boom-tip velocities are taken as zero and Cv comes from vessel motion.

Under the General Method in Table 3 of the 6th edition, a fixed structure takes 1.33; a TLP or spar 1.33 + 0.003 x Hsig; a semisubmersible 1.33 + 0.0007 x Hsig squared; and a drillship or FPSO 1.33 + 0.0012 x Hsig squared, each not less than 1.4 on a floating unit, with Hsig in feet. At a 20 ft significant wave height that gives 1.61 on a semisubmersible and 1.81 on an FPSO.

When may a flat dynamic coefficient of 2.0 be used under API Spec 2C?

Only under the Default Dynamic Method of the 6th edition, which is limited to fixed platforms in mild sea and wind conditions such as the Gulf of Mexico, and only where the supply vessel is held in a constant position relative to the platform, for example a platform-tethered supply vessel.

Offboard lifts then take Cv 2.0, offlead and wind may be taken as zero, and the sideload is 2 percent of the vertical design load, 0.02 x 2.0 x SWL.

What minimum hoisting speed does API Spec 2C require?

Unless otherwise agreed with the purchaser, the 6th edition requires a minimum steady hoisting velocity of Vhmin = 0.1 x (Hsig + 3.3) ft/s, with Hsig in feet, so that a load lifted off a heaving supply-boat deck clears it before the next wave brings the deck back up into it.

At a 6.6 ft (2 m) significant wave height that is 0.99 ft/s, about 0.30 m/s.

Does SOLAS regulation II-1/3-13 apply to offshore cranes?

Only in part. Regulation II-1/3-13, added by resolution MSC.532(107) and in force since 1 January 2026, covers lifting appliances on SOLAS ships, including personnel-handling cranes.

Paragraph 1.2 excludes appliances on ships certified as mobile offshore drilling units and on offshore construction ships engaged in pipe or cable laying, repair, offshore installation or decommissioning where the appliances comply with standards acceptable to the Administration. Paragraph 1.2 lists further exclusions, but these two are the ones that matter offshore. A platform supply vessel’s deck crane is within scope; a construction vessel’s main crane usually is not.

Which rules govern cranes on US Outer Continental Shelf platforms?

30 CFR 250.108 requires every crane on a fixed OCS platform to be operated to API RP 2D, and requires API Spec 2C for all cranes on a fixed platform installed after 17 March 2003 and for any crane manufactured after that date and installed on a fixed platform.

Each crane needs a functional anti-two-block device. Cranes on floating facilities and vessels fall under US Coast Guard rules rather than this section.

Which editions of API Spec 2C and RP 2D does the US regulation incorporate?

30 CFR 250.198 incorporates API Spec 2C 6th edition (March 2004) and API RP 2D 6th edition (May 2007).

BSEE’s incorporation-by-reference final rule published on 10 June 2026 (91 FR 35304, effective 10 August 2026) did not move them to Spec 2C 8th edition and RP 2D 7th edition; BSEE stated it will repropose that update in a future rulemaking, so the 2004 and 2007 editions remain the legal baseline.

What crane records must a US OCS fixed platform keep?

Under 30 CFR 250.108(e), design and construction records, including anti-two-block installation records, are kept for the life of the crane; inspection, testing and maintenance records, and the qualification records of the crane operator and all rigger personnel, are kept for at least 4 years.

All of them are kept at the OCS fixed platform.

What is the current edition of API Spec 2C, and does it cover ship cranes?

The current edition is the 8th, including Errata 1 (2021), reaffirmed in 2025.

The 8th edition extended the scope to shipboard cranes, which the 6th edition excluded. The US regulation still binds OCS fixed-platform cranes to the 6th edition, so a crane can be designed to the 8th edition for its class and buyer while being checked against the 6th for 30 CFR 250.108.

What is the difference between EN 13852-1, EN 13852-2 and EN 13852-3?

EN 13852-1:2025, published April 2025 and superseding the 2013 edition, covers general-purpose offshore cranes.

It excludes floating cranes, light offshore cranes and cranes with 2D or 3D motion compensation. Floating cranes are covered by EN 13852-2 (2014) and light offshore cranes by EN 13852-3 (2021).

Which standards does Norway require for cranes on mobile offshore units?

The Norwegian Maritime Authority’s Regulations of 21 December 2017 No. 2381, in force 1 January 2018, require offshore cranes on Norwegian mobile offshore units to reach the safety level of EN 13852-1:2013 or DNVGL-ST-0378 (May 2016), or an equivalent standard from another MOU classification society.

Loose gear follows NORSOK R-002 Edition 3 (March 2017), use of cranes and loose gear follows NORSOK R-003 Edition 3 (June 2017), and wire rope care and discard follow NS-ISO 4309:2010.

Can personnel be transferred by crane to a Norwegian mobile offshore unit?

Yes, under conditions. Section 25(3) of the NMA crane regulation allows transfer of personnel to and from the unit only when warranted by special circumstances, with the offshore installation manager’s approval in consultation with the safety representatives, and within the weather restrictions stated on the lifting-equipment certificates; where none are stated, NS-EN 13852-1:2013 paragraph 7.2.5 applies.

Only cranes and lifting appliances certified for lifting personnel may be used.

What emergency capability must a personnel-rated offshore crane have in Norway?

Section 8(2) of the NMA Regulations 2017 No. 2381 requires an offshore crane approved for personnel lifts to have an emergency operation system available within one minute, so a person on the hook can be landed after a power or control failure.

Cranes with a delivery contract before 1 January 2018 are exempt where the company documents the safety of personnel.

How much can an API Spec 2C crane lift when it carries personnel?

The personnel rating is the least of 33 percent of the crane’s calculated non-personnel safe working load, the load allowed by the hoist reeving and wire rope design factor, and the available hoist line pull (API Spec 2C 6th edition, 4.1.2).

The load hoist wire rope must have a design factor of at least 10 when handling personnel (7.2.4.3).

What wire rope design factor does API Spec 2C require?

The 6th edition requires hoist system wire rope to have a design factor not less than 2.5 x Cv or 5.0, whichever is greater (7.2.4.1), and standing ropes such as boom pendants not less than 2.0 x Cv or 4.0, whichever is greater (7.2.4.2).

Up to Cv 2.0 the fixed minimum of 5.0 governs the hoist rope; above it the Cv term governs, so a crane with Cv 2.4 needs a hoist rope design factor of 6.0. Personnel hoisting needs 10.

How often must lifting equipment be thoroughly examined in the UK?

Under the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER, SI 1998/2307), HSE guidance gives thorough examination every 6 months for lifting accessories and for lifting equipment used to lift people, and every 12 months for all other lifting equipment, unless an examination scheme drawn up by a competent person sets other intervals.

What are the IMCA lift categories?

IMCA M 187 (also numbered D 060, HSS 019 and LR 006), Guidelines for lifting operations, current at Rev. 2.1 of June 2023, sorts lifts into routine, non-routine and engineered, the categories its Rev. 1 of March 2018 defines.

Every lift needs a lift plan. A routine lift runs on a generic lift plan and job risk assessment; a non-routine lift needs a specific plan and a pre-lift meeting; an engineered lift needs detailed engineering by an onshore organization. Where the category is in doubt, the lift is treated as non-routine.

Is lifting a person by crane a routine lift?

No. Under the IMCA lifting guidelines, lifting personnel is a non-routine lift.

The one exception the guidance names is divers deployed in a launch and recovery system that complies with its design requirements, which may be treated as a routine lift.

Who prepares an engineered lift plan?

An onshore engineering organization working to established engineering standards and procedures, under the IMCA engineered-lift category.

The plan carries structural assessments, dimensional checks, rigging design calculations, environmental limits and drawings, and where the vessel counter-ballasts during the lift it includes a stability check for sudden accidental loss of the hook load.

Which IMCA document covers personnel transfer by crane?

IMCA M 202 (also HSS 025 and LR 012), Guidance on the transfer of personnel to and from offshore vessels and structures, Rev. 2.2, March 2024.

Walk-to-work gangway transfer has its own document, IMCA M 254, Guidelines for walk to work operations, Rev. 1, August 2025.

Which IMCA documents cover heavy-lift slings and wire rope?

IMCA M 179 (LR 008), the code of practice on the manufacture and safe use of cable-laid slings and grommets, Rev. 2, April 2025; IMCA M 237 (LR 009) on high-performance fiber slings for engineered lifts, Rev. 1.1, February 2024; IMCA M 194 on wire rope integrity management, Rev. 4, October 2023; and IMCA M 197 on magnetic rope testing, Rev. 2, July 2024.

Which wire rope discard standard applies offshore?

ISO 4309:2017, Cranes: Wire ropes: Care and maintenance, inspection and discard, is the current edition, and a revision is under way.

Norway’s NMA crane regulation for mobile offshore units still names NS-ISO 4309:2010, so a Norwegian MOU follows the older edition unless an equivalent is accepted.

What is the largest crane vessel lifting capacity?

On operator figures: Heerema’s Sleipnir carries two 10,000 t cranes and lifts up to 20,000 t in tandem, and lifted the 15,300 t Leviathan topside in September 2019; Heerema’s Thialf has a lift capacity of 14,200 t; DEME’s Orion has a 5,000 t main crane.

Allseas’ Pioneering Spirit lifts topsides of up to 60,000 t and jackets of up to 20,000 t in a single lift with dedicated lift systems, and carries a 5,000 t special-purpose crane.

When is a float-over chosen instead of a crane lift?

When the topside exceeds the capacity of the crane vessels available for the campaign, or when a float-over is the cheaper or better-suited option at the site, for example where no crane vessel can be mobilized in the window.

Weight alone does not force it: Sleipnir lifted a 15,300 t topside in 2019 and Pioneering Spirit is rated for 60,000 t topsides.

What standard covers the marine warranty survey of a lift?

DNV-ST-N001, Marine operations and marine warranty, Edition 2023-12, covers marine operations during development or decommissioning of an offshore asset and sets marine warranty survey requirements for load-out, construction afloat, voyages and installation or removal.

It harmonized the legacy DNV offshore standards and the GL Noble Denton guidelines.

What is the current edition of DNV-RP-N103 and DNV-ST-0378?

DNV-RP-N103, Modelling and analysis of marine operations, is Edition 2017-07, amended 2021-09.

DNV-ST-0378, Offshore and platform lifting appliances, is Edition July 2019, amended October 2021, superseding the May 2016 DNVGL-ST-0378; the October 2021 amendment added a documentation requirement for a risk analysis of offshore cranes covering accidental drop of the hoisted load.

Why does a wide sling angle increase sling load?

Each leg of a multi-leg sling carries its share of the vertical load divided by the cosine of the leg angle from vertical.

At 45 degrees the factor is 1.41 and at 60 degrees it is 2.0, so a two-leg sling at 60 degrees puts the full object weight into each leg. A spreader bar holds the legs near vertical to keep that factor close to 1.0, at the cost of its own weight and a compression check on the bar.

What is a snap load?

A snap load is a shock in the lift wire when it goes slack and then re-tensions abruptly.

In the splash zone a wave or buoyancy can lift an object faster than the wire pays out; when the water drops away the object falls back onto the slack wire and snatches it tight. The peak can exceed the wire’s rating and drop the object, which is why the lift analysis sets the limiting sea state so that the wire tension stays positive through the crossing.

Why is lifting offshore harder than lifting onshore?

Three conditions that an onshore crane does not face: the crane base moves with the vessel, so the load accelerates before it leaves the deck; the load may pass through the sea surface and pick up slamming, buoyancy, added mass and drag; and the operation can only run inside a weather window with a named significant wave height and wind limit.

Each one raises the dynamic load above the static weight, which is why API Spec 2C sets higher minimum dynamic coefficients on floating installations (1.40) than on fixed ones (1.33).

What does a semi-submersible crane vessel do that a barge crane cannot?

A semi-submersible crane vessel floats on submerged pontoons joined to the deck by columns, so its waterplane area is small and its heave, roll and pitch response to waves is much lower than a barge’s.

That lets it lift in open-sea conditions that weather-bind a barge, and on the largest units two cranes work in tandem: Sleipnir’s two 10,000 t cranes lift up to 20,000 t together.

Sources

  1. 30 CFR 250.108. requirements for cranes and other material-handling equipment on OCS fixed platforms (API RP 2D, API Spec 2C after 17 March 2003) ecfr.gov
  2. BSEE final rule 91 FR 35304, 10 June 2026. documents incorporated by reference (API Spec 2C and RP 2D update deferred to reproposal) federalregister.gov
  3. Norwegian Maritime Authority. Regulations of 21 December 2017 No. 2381 on cranes and lifting operations on mobile offshore units sdir.no
  4. HSE. Thorough examination of lifting equipment under LOLER 1998 (6 and 12 month intervals, examination scheme) hse.gov.uk
  5. IMCA Guidance Document Register, 1 June 2026. M 187 Guidelines for lifting operations Rev. 2.1, M 202 Rev. 2.2, M 179 Rev. 2 imca-int.com
  6. IMO MSC.532(107), 8 June 2023. SOLAS regulation II-1/3-13 on lifting appliances, in force 1 January 2026 imo.org
  7. DNV-ST-N001. Marine operations and marine warranty, Edition 2023-12 dnv.com
  8. DNV-RP-N103. Modelling and analysis of marine operations, Edition 2017-07, amended 2021-09 dnv.com
  9. Heerema Marine Contractors. Sleipnir semi-submersible crane vessel (two 10,000 t cranes, 15,300 t Leviathan topside) heerema.com
  10. Heerema Marine Contractors. Thialf semi-submersible crane vessel (14,200 t lift capacity) heerema.com
  11. Allseas. Pioneering Spirit vessel specifications, February 2026 (60,000 t topsides, 20,000 t jacket lift systems, 5,000 t special-purpose crane) allseas.com
  12. DEME. Orion offshore heavy-lift DP3 installation vessel (5,000 t main crane) deme-group.com